House site cleanup progress
22 Apr 09
Below is some basic statistics provided GROCON.
- 323 registered sites for cleanup from Labatouche to Devon North (Gippsland fire affected areas).
- 60 sites do not have consent signed off.
- 23 sites completed and 7 sites are being worked on at the moment.
- 7 teams are working and GROCON is planning to increase this to 15 teams.
- 3 community liaison officers working in area mainly organising consents.
- Planning to have all consents signed of by end of April with deadline of end of May.