House site cleanup progress

22 Apr 09

Below is some basic statistics provided GROCON. 

  • 323 registered sites for cleanup from Labatouche to Devon North (Gippsland fire affected areas).
  • 60 sites do not have consent signed off.
  • 23 sites completed and 7 sites are being worked on at the moment.
  • 7 teams are working and GROCON is planning to increase this to 15 teams.
  • 3 community liaison officers working in area mainly organising consents.
  • Planning to have all consents signed of by end of April with deadline of end of May.